Texas public works payment bond claim deadlines
Compare Texas public payment-bond claim notices, second- and third-month steps, sworn account evidence, retainage and separate suit deadlines.

Direct answer
For covered Texas state/local public-work bond claims, Section 2253.041 generally requires a claim notice and sworn account to the prime contractor and surety by the 15th of the third month after each claimed work month. A claimant without a direct prime contract also reviews the second-month prime-contractor notice under Section 2253.047. Retainage and suit timing have separate rules.
Public work uses a payment bond instead of a lien on public property
A crew can perform the same trade work on two projects and face different remedies because one owner is private and the other is a governmental entity. Texas Government Code Chapter 2253 covers performance and payment bonds for many public works contracts.
For payment tracking, the first question is not simply whether money is overdue. Confirm who owns the project. A city, county, school district, university or state agency can point the file toward a public-work bond claim rather than the private-project lien calendar.
Do not record a public project as a private commercial job merely because the prime contractor is a private company. The owner and contracting arrangement matter.
Payment bond vs. performance bond: locate the right document
Under Government Code Section 2253.021, a payment bond protects qualifying labor and material payment beneficiaries. A performance bond protects the governmental entity against a failure to perform the work. A performance-bond certificate is not a substitute for the actual payment bond when the office is assembling an unpaid-work claim file.
The phrase subcontractor payment and performance bond can also describe bonds a subcontractor furnishes under its own agreement. Identify the principal, obligee, covered contract and beneficiary language on the actual instrument before assuming that your unpaid invoice is covered.
Keep Texas state/local public work, federal work and private bonded work in separate review paths. Property Code Chapter 53 Subchapter I addresses a private-project payment-bond framework. This public-work guide does not supply that framework’s claim calendar. Use the project information-request guide to organize missing documents.
| Document or project | What to verify | Next review |
|---|---|---|
| State/local public payment bond | Covered contract, surety and claimant relationship | Applicable Chapter 2253 claim requirements |
| State/local public performance bond | Governmental obligee and performance obligation | Do not treat as the payment-claim instrument |
| Private-project payment bond | Actual bond and Chapter 53 applicability | Separate private bonded-project analysis |
| Bond furnished by a subcontractor | Principal, obligee and beneficiary terms | Determine whose obligations it secures |
Request the bond and prime-contract information early
A useful bond file identifies the prime contractor, surety, bond number, penal sum and governmental entity. Chapter 2253 includes provisions for obtaining contract and bond information. Waiting until payment stops can cost valuable review time.
Store the actual bond document rather than a typed surety name copied from an email. Confirm the claims address and compare it with the statutory recipient requirements. If the project has multiple phases or contracts, verify that the bond matches the work your company performed.
- Governmental entity and public-work contract number
- Prime contractor's full legal name
- Surety's legal name and claim address
- Payment bond number and copy of the bond
- Claimant's written agreement and contractual tier
- Labor and material records separated by month
The ordinary bond notice is tied to the work month
Section 2253.041 requires a payment bond beneficiary seeking recovery in a bond suit to mail written notice of the claim to the prime contractor and surety. The statute states that the notice must be mailed on or before the 15th day of the third month after each month in which claimed labor was performed or material delivered.
The notice is accompanied by a sworn statement of account. Chapter 2253 then supplies different content rules for written agreements, claims without written agreements, multiple items, unit-price work and retainage. The correct package depends on the file.
Service is not an administrative detail. Section 2253.048 addresses registered or certified mail. Check the current statute and obtain legal review for the actual claim instead of copying the delivery method from a private-project form.
Worked example: material delivered in two months
Hypothetical example: a supplier delivers unpaid material to a public school project in February and March 2026. The supplier should preserve delivery tickets for each month rather than treating the final invoice as the only date.
Using Section 2253.041's third-month pattern, the February delivery month points to May 15 and the March delivery month points to June 15. The notice review should identify the prime contractor, surety, written agreement and sworn account before those dates.
This example does not decide whether the supplier qualifies or whether additional lower-tier notices apply. It shows why the office needs two work-month rows even if accounting issued one invoice.
| Delivery month | Illustrative notice date | Evidence to attach |
|---|---|---|
| February 2026 | May 15, 2026 | February tickets, invoice allocation and account statement |
| March 2026 | June 15, 2026 | March tickets, invoice allocation and account statement |
Lower-tier claimants may have an earlier additional notice
A claimant without a direct contractual relationship with the prime contractor should not stop after reading Section 2253.041. Section 2253.047 contains additional notice provisions, including an earlier notice directed to the prime contractor for certain unpaid labor or material.
This is where a simple 'bond claim due date' field fails. The system needs the claimant's tier, each work month, recipients and each separate event. A lower-tier supplier may need more than one notice step before any suit question arises.
Retainage is also addressed separately in Section 2253.046. Keep retained amounts apart from ordinary unpaid labor or material so the reviewer can apply the right rule.
Public-work payment bond checklist
- Confirm the governmental owner and public-work contract
- Obtain the payment bond and identify the correct surety
- Record whether the claimant contracted with the prime contractor
- Separate unpaid labor and material by calendar month
- Preserve the written agreement, changes and delivery records
- Prepare the sworn account information from reconciled books
- Review Sections 2253.041 through 2253.048 for the claim type
- Track any additional lower-tier notice separately
- Save registered or certified mailing evidence
- Do not treat the notice date and suit date as the same event
- Have Texas construction counsel review a live claim
Separate the ordinary notice, lower-tier notice and suit
Identify whether the governing project is Texas state/local public work, federal work or a private bonded project before using this table. Chapter 2253 is not the federal Miller Act or the private Chapter 53 bond system.
| Step | Ordinary timing / trigger | Recipient or action |
|---|---|---|
| Labor/material claim, 2253.041 | 15th of month 3 after each claimed work month | Notice and sworn account to prime contractor and surety |
| No direct prime contract, 2253.047(c) | 15th of month 2 after each unpaid work month | Additional notice to prime contractor |
| Retainage, 2253.046 | 90 days after final completion of public work contract | Notice to prime contractor and surety, unless covered in a prior claim |
| Earliest payment-bond suit, 2253.073 | Claim not paid before day 61 after notice mailed | Qualified litigation review |
| Payment-bond limitations, 2253.078(b) | First anniversary of claim-notice mailing | Do not calculate from final invoice or lien filing |
Public payment-bond FAQs
Can I use the private lien notice form? Do not assume so. Bond notices, sworn-account support and delivery requirements follow their own law.
Does the third-month surety notice replace a lower-tier second-month notice? Treat them as separate requirements for review. A direct contractual relationship with the prime changes the tier analysis.
Is every public project bonded? Verify the actual project, required bond and available remedies. A missing bond is a legal review issue, not a reason to mark the claim complete.
Does a payment complaint to the agency complete the statutory bond notice? Not automatically. Keep the complaint and the reviewed bond-notice tasks separate.
Related reading
- Compare private-project monthly notice deadlines
- Review the private-project mechanics lien timeline
- Texas retainage notice requirements for subcontractors
- Texas specially fabricated materials: current notice and lien rules
Turn project facts into a review queue.
Keep unpaid work months, parties, invoices, documents and estimated review dates in one private workspace.
Create your free accountOfficial sources
- Texas Government Code Chapter 2253
- Official Texas Government Code Chapter 2253 PDF
- Texas Government Code Section 2253.021: payment and performance bond purposes
- Texas Property Code Chapter 53 Subchapter I: private-project payment bonds
Source note: Reviewed October 14, 2026. Verify the current statute and obtain qualified advice for a specific project or claim.